I am working on an upgrade from Windchill10.0 mo40 running on Oracle 11g

I would like to upgrade to Windchill 11.0 m030 running on Oracle 12c.

 

Do I need to do anyjthing special to do this or will the Upgrade Manager handle all of the updates to Windchill and the Oracle schema?

 

Best answer by SergeyEfimov

WinDU tasks for 10.2 is enough.
I upgraded system from 10.1 to 11.0 there the WinDU tasks also only for 10.2.
You must use export/import dump procedurу for oracle.

3 replies

1-Visitor
July 24, 2017

You need to run WinDU tasks for Upgrade preparation.
Export/import oracle database to dump file.

BenLoosli23-Emerald IIIAuthor
23-Emerald III
July 24, 2017

That is a problem with the way PTC has mishandled WinDU!

I have run WinDU for the 10.2 upgrade, but PTC did not release WinDU patches for a 10.0 to 11.0 upgrade.

All of the Upgrade for 10.2 WinDU checks come back with no errors and a few warnings. A complete WinDU run does the same.

 

That is my plan for the database, export from the 11g and import to 12c, then run Upgrade Manager.

1-Visitor
July 24, 2017

WinDU tasks for 10.2 is enough.
I upgraded system from 10.1 to 11.0 there the WinDU tasks also only for 10.2.
You must use export/import dump procedurу for oracle.