Question
Sync Affected objects in CN while using Redline.
- When i create a CN1(Full Track) with Part XYZ(BOM top Level) with revision A.2 in released state as affected object only and do submit later.
- Create a Redline 1 for the Part XYZ and then move the CN1 to Pending Implementation state.
- Then i create a CN2(Fast Track) for the same Part XYZ with revision A.2 in released state as affected objects and do submit later.
- Create a Redline 2 for Part XYZ and then do a revise in implementation plan and the Redline 2 is successfully incorporated into Part XYZ B.1
- Now when i cone back to the CN1 which is in pending implementation state. The affected object shows Part XYZ in A.2 version and does not get refreshed to Part XYZ B.1 Released version.
What needs to be done so that the Affected objects are refreshed automatically.