Automatic calculate on save

  • December 15, 2012
  • 2 replies
  • 2239 views

Why did PTC implement automatic worksheet recalculation on saving? It has caused me so many delays when saving large worksheets when I forget to deselect "automatic calculation". Is there any way to deactivate it? Are there other users who find this functionality useful?

2 replies

1-Visitor
December 18, 2012

You can disable auto calculation in general from the Calculation tab:

Untitled.png

1-Visitor
December 18, 2012

Hi Roger I want automatic calculation in effect whilst I'm adding code. What I don't want is for the sheet to recalculate on saving. I don't think V13 did that certainly v10 did not. I don't see why anyone would want that feature and I don't think it can be disabled, but I amy be missing something.

Dave

1-Visitor
December 18, 2012

Dave, you are correct. I just had a quick chat with development and was informed that calculating during save was implemented from Mathcad 12 through 15. There are actually some legacy reasons why that was done, and I can't say I agree with them. In any case, Prime now reverts back to the earlier days, i.e. it does NOT auto calculate upon saving a worksheet.

1-Visitor
December 18, 2012

By the way, this thread may be of some relevance to you:

http://communities.ptc.com/thread/38421

1-Visitor
December 18, 2012

Thanks Roger that was helpful. That at least is one advantage of switching to Prime once it has the same fuctionality as Mathcad 15. Mathcad 14 &15 are currrently the preferred option for our research group with one person using Matlab.

Dave