Question
How do you handle ECN's that Require Tooling changes?
The fundamental issue: Does change management cover the defining product data only, or also physical items?
Every successful change management system must somehow address physical items, but the key for Windchill administration is where does a change end in Windchill, and how do people get notified that they need to address physical things, etc. (is this done via Windchill or other).
Seems that the most logical way to handle is:
- Change management in Windchill addresses data only
- Each Windchill change needs to be somehow communicated to the business system (SAP, etc.)
- The business system needs to be used to manage assignments, etc. for handling physical items, which may include
But - we know that people handle this in many very different ways. Interested in the opinions of others on this and how others handle it.
Every successful change management system must somehow address physical items, but the key for Windchill administration is where does a change end in Windchill, and how do people get notified that they need to address physical things, etc. (is this done via Windchill or other).
Seems that the most logical way to handle is:
- Change management in Windchill addresses data only
- Each Windchill change needs to be somehow communicated to the business system (SAP, etc.)
- The business system needs to be used to manage assignments, etc. for handling physical items, which may include
But - we know that people handle this in many very different ways. Interested in the opinions of others on this and how others handle it.