Locking Change Activity Tasks
Let me first explain the problem.
We currently use an ECN for the release of items (parts, documents and CAD drawings/models)in PDMLink v9 M040. The items being released are added to the Resulting Objects of the Change Task associated to the ECN. A fairly complex workflow is initiated which includes peer review, approval, and authorisation steps in the Release Process.
The lifecycle that the items pass throughduring this workflow are IN-WORK, UNDER REVIEW, PRE-RELEASED and RELEASED
Once the release process completes and the items are setto RELEASED,the user can look at the changes related to the item to look at the release history.
We have a local requirement to allow selected users to perform very simple "typo" corrections (e.g. spelling mistakes)to RELEASED information. The process here relies on raising a Problem Report and Problem Report Action which allows the assignee of the action permission to set the item back to IN-WORK, make the amendment, and then re-release at the same REVISION. The item will iterate due to the check-out/check-in.
Now the problem: if a user looks at the Change Task associated to the initial release,the Resulting Objects on the task now show the latest iteration ... not the iteraion when the original release took place.
So my question: does anyone know of a method to"lock" a Change Task so that the iteraion showing for the Affected/Resulting Objects are fixed at the point that theChange Task is completed?
Many thanks for any help.