Hello Everyone,



Hope someone could help. I am customizing the PR Workflow Approval activity to complete when the first vote is "Reject or Rework” The participants role is required and All must vote. The tally code waits until all required participants vote, my goal is to keep it that way as long as participants are voting "Approve" continue on running, but the first (Reject or Rework) vote, kill all tasks and proceed. Is this possible?


1 reply

1-Visitor
April 17, 2014

Check attachment "Reject on 1st Reject Vote.pptx" in the following post. It may help you.