Has anyone else had the issue the resultant objects are not set back to released upon resolution of Change Notice? We see it all the time that the CN will leave objects at under review state.

PTC document:

CS111383

TitleNew revised change notice workflow hangs on “Synch on CA Complete” workflow expression in Windchill PDMLink 10.0
Description
  • New revision of Change Notice workflow loses its synchronization with related Change Activities object
  • After revision the Change Notice workflow cannot be completed
Applies ToWindchill PDMLink 10.0
Cause
Resolution
  • Reported to R&D as SPR 2163673
  • Workaround: Set the sequence on Change Activity creation.