Question

WC Calendar

  • March 12, 2014
  • 2 replies
  • 1354 views

WC 10.1 M040


I am looking to change the way the calendar in WC views the calendar days associated to the workflow.


What I need WC to do is only account only for working days when calculating the due date of a workflow. Currently it does not exclude Saturday & Sunday when making the calculation.


I have no idea what setting to look for to change this or what it needs to be set to, to exclude the weekends.



Any help will be greatly appricheated.





Marshall Sexton
Master Modeler


NABI USA

2 replies

22-Sapphire I
March 12, 2014
[cid:image001.png@01CF3DE9.B4C3D140]
1-Visitor
March 12, 2014
I never did get my workflows to adjust deadlines based on the System Calendar weekend non-working days. So, I'd love to hear of any success here.

Kind regards,

Vaughn McDaniel III
Engineering Services Group - PLM/CAD Applications

[cid:image002.png@01CF3DF8.F81456E0]